Home / Method Statements / Diesel Generator Engine Installation Method Statement Procedure

Diesel Generator Engine Installation Method Statement Procedure

Prior to commencement of DG set installation work all shop drawing will be submitted for approval and approval will be obtained  from the consulting engineer. Approved shop drawing will show the routes with reference  numbers  as well as the supporting  requirements.  Only approved  shop drawing will be used at the site for installation. All materials  to be used in this system will be submitted  for Engineer’s  Approval in forms of material submittal or Product data. Only approved  materials will be stored ant used at the site.

Prerequisites for Diesel Generator DG Set Installations

Make sure that the Generator Room is ready to accept the generator set.

Advertisement:

Confirm that the access to the generator room is free from any obstacles.

Move the Generator set in place following the manufacturer handling instruction.

Lifting the generator set

Allocate trained personnel to ensure the lifting and transportation of the generator in a safe manner and in accordance to local guidelines. Before lifting the generator set, lifting points, angle of slings, mass access to intended site and the distance of movement should all be taken into account when organizing suitable crane/hoist.

Positioning Generator set using a Forklift Truck

The dimension, mass and route to be taken onto account when selecting an appropriate lifting trucks. After get the appropriate truck, position the arm of the forklift under a frame or pallet. Lift and handle the equipment slowly. Set down the generator set in final position slowly

Access to Diesel Generator DG Set

Provide at least 1 meter (3.3 feet) of clearance on all sides of the diesel generator set for maintenance and service access. A raised foundation or slab of 152mm (6 inches) or more above floor level will make servicing easier. Lighting should be adequate for operation, maintenance and service operations and should be connected on the load side of the transfer switch so that it is available at all times. Mount the generator set on a substantial and level base such as concrete pad. A non-combustible material must be used for the pad. Use 16mm or anchored mounting bolts to secure the generator The 38mm x 152mm pipe inserted over the mounting bolts to align them to the holes in the bedframe. (see fig. below)

dg set installation porocedure

Vibrator Isolator Installation

Place the vibrator isolator (FSR Mounting – Free Standing Bolted) under the support point of the equipment, ensure that the load is uniformly distributed over the top plate of the vibration isolator as shown in Figure A and B below:

dg set installation method vibration isolator porocedure

Adjust the FSR mounting: With the 6 mm spacer in position as shown, tighten the positioning nut. Turn, adjusting bolt of the spring counter-clockwise to load the spring. Load all the FSR at the same time to ensure that the total load is uniformly spread onto all the FSR mounts. Continue until the spring the spring load equal to the load of the requirement. When the equilibrium point is reached, the 6 mm spacer can be removed from the FSR mount (see fig B above).

Moving the Generator Set

Ensure that the crane operating area is able to support the mass of the crane and the generator set. Attach the lifting device to the lifting points only, using suitable shackles, chains and spreader bars. Slowly tighten the slings. Inspect the lifting attachments before commencing a full lift to ensure they attached correctly. Hoist generator set slowly using the indicated lifting points only. Guide the generator set with ropes at a safe distance, to prevent uncontrolled rotation when positioning the generator set. Move the generator set on the desired location and place in position, bring the set down slowly. Loosen the slings, unhook and remove the shackles.

Mechanical Connections to Diesel Generatot DG Set

Fuel system: Cleanliness is of the utmost importance. Make every effort to prevent entrance of moisture, dirt or contaminants of any kind into the fuel system. Clean all fuel system components before installing

Fuel Return Restriction Limit: Fuel return drain restriction between the engine injector return line connection and the fuel tank must not

exceed the limit stated in the model-specific generator set specification sheet.

Fuel Lines Routing: A flexible fuel hose or section of flexible fuel hose must be used between the engine’s fuel system and the fuel supply and return lines to protect the fuel system from damaged.

Engine Fuel Connection: Identification tags are attached to the fuel supply line connection. All generator set require a fuel return line from injector to the tank.

DG set fuel connection diagram

DC Control Wiring

TB1 Remote Monitor I Control Connection – Customer monitor/control connections are attached to terminal block TB1. Optional Equipment such as sensing devices used to monitor generator set operation, remote start/stop switches, etc. are also attached to TB1.

TB1 Wiring: Digital Connection. Connection points, other than relayed outputs and network are considered digital connection to terminal strip TB1. The type/gauge wire to used for these connection are:

  • Less then 305 meters, (1000 feet) use 20 gauge stranded copper wire
  • 305 to 610 meters (1000 to 2000 feet), use 18 gauge stranded copper wire

Relay Due to wide variety of devices that can be attached to the relay outputs of TB1, installer must determine the gauge of the stranded copper wire will be used at the site installation.

AC Electrical Connections

Before making any AC electrical connections, ensure that the generator set cannot be accidentally started. Make sure the operator panel is in OFF mode. Turn off or remove AC power from the battery charger and then removed the negative(-) battery cable from the set starting battery.

Transfer switch: Transfer switch must be used for switching the load from normal power source to the generator set (see figure below)

dg set load connection diagram

Load Connection:  All loads are connected to the generator by bolting stranded load wire to the appropriate terminals on the generator re-connection terminal block or circuit breaker lugs. The terminal are marked U, V, W and N to indicate the line and neutral connection (reference: U, V, W and N correspond with L1, L2 and L3; and N with LO respectively)

Grounding: The figure below shows the description of system and equipment grounding of permanently installed AC generators within facility wiring system. It also illustrates typical system grounding for a 3 pole ATS, note that the generator neutral is connected to the ATS and it is not bonded to the grounded at the generator. In the 4 pole ATS system, a grounding electrode conductor and a bonding jumper are used to connect the generator neutral to ground.

DG set Grounding connections

Check Also

cable tray bends and offset fabrication table

Typical Limiting Values of Electrical Substation Equipments

On this page you can find permissible limits for different equipment’s which are part of …

Leave a Reply

error: Content is protected !!